The key metrics tracked in a Kanban system include work in progress (WIP), lead time, and cycle time. WIP refers to the number of tasks currently being worked on. Lead time is the total time from the moment a new task is added to the backlog until it's completed. Cycle time is the time it takes for a task to go from start to finish once it's actively being worked on.